docs(state): record phase 3 context session — Phase 3 discuss-phase complete

state.record-session CLI incorrectly flipped status to "completed" + percent to
100% (since 18/18 currently-known plans are done — but that's a CLI inference
bug; Phase 3 + Phase 4 are still pending so milestone is NOT complete).

Restored: status=ready_to_plan, percent=50% (2/4 phases truly complete).

Phase 3 CONTEXT.md at:
  .planning/phases/03-spec-10-smoke-verification-dom-event-log-verification/03-CONTEXT.md
DISCUSSION-LOG.md sibling captures the alternatives considered.

5 plans + 4 D-P3-* locked decisions ready for /gsd-plan-phase 3.

Co-Authored-By: Claude Opus 4.7 (1M context) <noreply@anthropic.com>
This commit is contained in:
2026-05-20 17:57:07 +02:00
parent dba51ea233
commit 2b4f0689fb

View File

@@ -3,9 +3,9 @@ gsd_state_version: 1.0
milestone: v2.0.0 milestone: v2.0.0
milestone_name: milestone milestone_name: milestone
status: ready_to_plan status: ready_to_plan
stopped_at: Phase 2 closed 2026-05-20 — 4/4 plans landed, UAT harness 29/29 GREEN, vitest 171/171 GREEN, bundle gates 6/6 PASS, verifier verdict PASSED (T5 override per user delegation + harness coverage). Phase 3 prep awaits. stopped_at: Phase 3 context gathered — 5 plans + 4 D-P3-* locked decisions; ready for /gsd-plan-phase 3
last_updated: "2026-05-20T18:00:00.000Z" last_updated: "2026-05-20T15:55:50.099Z"
last_activity: 2026-05-20 -- Phase 02 closed last_activity: 2026-05-20
progress: progress:
total_phases: 4 total_phases: 4
completed_phases: 2 completed_phases: 2
@@ -215,9 +215,9 @@ Items acknowledged and carried forward from previous milestone close:
## Session Continuity ## Session Continuity
Last session: 2026-05-20T15:30:00.000Z Last session: 2026-05-20T15:55:50.071Z
Stopped at: /gsd-resume-work loaded HANDOFF.json (a440c7d). Phase 1 closed; Phase 2 planning complete (4 plans validated, plan-checker iter-2 GREEN). Awaiting user direction on `/gsd-execute-phase 2` (canonical) vs `--wave 1` (RED tests only). Stopped at: Phase 3 context gathered — 5 plans + 4 D-P3-* locked decisions; ready for /gsd-plan-phase 3
Resume file: .planning/phases/02-stabilize-export-pipeline/.continue-here.md (sibling to consumed HANDOFF.json) Resume file: .planning/phases/03-spec-10-smoke-verification-dom-event-log-verification/03-CONTEXT.md
Prior session: 2026-05-20T12:54:42.000Z — /gsd-pause-work saved Phase 2 execution-ready handoff (a440c7d); Phase 1 closed end-to-end via verifier audit GREEN (586836f); alpha distribution shipped (dist-archives/mokosh-build-2026-05-20-6dbed91.zip) Prior session: 2026-05-20T12:54:42.000Z — /gsd-pause-work saved Phase 2 execution-ready handoff (a440c7d); Phase 1 closed end-to-end via verifier audit GREEN (586836f); alpha distribution shipped (dist-archives/mokosh-build-2026-05-20-6dbed91.zip)
Earlier session: 2026-05-20T12:00:00.000Z — Plan 01-10 closed via cycle-2 operator ack "All good" + 5 inter-cycle debug fixes + brand-rename follow-up Earlier session: 2026-05-20T12:00:00.000Z — Plan 01-10 closed via cycle-2 operator ack "All good" + 5 inter-cycle debug fixes + brand-rename follow-up