docs(roadmap): re-phase milestone — remove Phase 2 (DOM/event-capture privacy)
...
Per operator charter shift 2026-05-20: "we don't care about privacy hardening.
At least here." Archive flow is internal-only (no external transmission),
which reframes the password-masking P0-5 defect from privacy-regulation
gravity to operator-hygiene polish.
Re-phasing applied across 4 planning artifacts:
ROADMAP.md:
- Original Phase 2 ("Stabilize DOM + event-capture privacy") REMOVED entirely
(summary list + Phase Details section + Progress table row).
- DOM + event-log VERIFICATION (REQ-rrweb-dom-buffer + REQ-user-event-log)
ABSORBED by new Phase 3 (SPEC §10 smoke verification).
- Phase numbering: old 3 → new 2 (export), old 4 → new 3 (smoke), old 5 → new 4
(optional harden). Dependency chains updated accordingly.
- Overview blurb + journey narrative + success criteria refreshed.
- Phase 3 (smoke) explicitly NOT-in-scope: P0-5 password masking dropped.
REQUIREMENTS.md traceability:
- REQ-rrweb-dom-buffer: Phase 2 → Phase 3 (verification scope; UAT harness
A24+ extension planned).
- REQ-user-event-log: Phase 2 → Phase 3 (same context).
- REQ-password-confidentiality: Phase 2 → Out of Scope (v1) — DEFERRED per
charter shift.
- REQ-popup-ui, REQ-screenshot-on-export, REQ-archive-layout,
REQ-meta-json-schema, REQ-archive-export-latency: Phase 3 → Phase 2
(renumbered; substantively shipped via Plans 01-08 + 01-09 + 01-12;
residual gaps in Phase 2).
- Coverage: 10 mapped + 1 out-of-scope (was 11 mapped).
PROJECT.md:
- CON-sensitive-data-masking: DEFERRED 2026-05-20 (preserves audit trail
via strikethrough; rationale documented).
- DEC-004 amendment: rrweb 5000-event cap retained; masking deferred. Cites
rrweb 2.0.0-alpha.4 maskInputSelector→maskInputFn API change.
STATE.md:
- frontmatter total_phases: 5 → 4.
- stopped_at narrative captures the re-phasing event.
CLI bug note: this re-phasing was attempted via `gsd-sdk query phase.remove 2`
+ canonical `/gsd-remove-phase 2` Skill invocation, but BOTH paths produced
corrupted output (cascading rename via reverse-iteration loop at
phase.cjs:670-679 collapsed all subsequent phases to "Phase 2", plus a
mysterious "2026"→"2002" date corruption). Recovery applied as manual edits
in this commit. CLI bug logged as upstream GSD-framework concern; not a
Mokosh-side issue.
Plan: next is `/gsd-discuss-phase 2` (new Phase 2 = export pipeline; narrowed
scope per re-phasing — ~2-3 plans expected since Plans 01-08 + 01-09 + 01-10
+ 01-12 already shipped most surface).
Co-Authored-By: Claude Opus 4.7 (1M context) <noreply@anthropic.com >