Milestone v1 (v2.0.0): Mokosh — Session Capture #1

Merged
strategy155 merged 297 commits from gsd/phase-04-harden-clean-up-optional into main 2026-05-31 15:34:17 +00:00
Showing only changes of commit 125269dcc5 - Show all commits

View File

@@ -4,8 +4,8 @@ milestone: v2.0.0
milestone_name: milestone milestone_name: milestone
status: executing status: executing
stopped_at: "Completed 04-08-PLAN.md (methodology reframe; A33 lands; ROADMAP SC #1 CLOSED via video-file MediaStream + SYNC install + LAZY first-frame; spike re-run 1.8MB vs 8505; UAT 34/34 + vitest 184/184 GREEN; architecture UNCHANGED per debug session-2)" stopped_at: "Completed 04-08-PLAN.md (methodology reframe; A33 lands; ROADMAP SC #1 CLOSED via video-file MediaStream + SYNC install + LAZY first-frame; spike re-run 1.8MB vs 8505; UAT 34/34 + vitest 184/184 GREEN; architecture UNCHANGED per debug session-2)"
last_updated: "2026-05-22T09:06:10.449Z" last_updated: "2026-05-22T09:07:54.692Z"
last_activity: 2026-05-21 last_activity: 2026-05-22
progress: progress:
total_phases: 4 total_phases: 4
completed_phases: 3 completed_phases: 3
@@ -29,9 +29,9 @@ no server, no password leaks.
Phase: 04 (harden-clean-up-optional) — EXECUTING Phase: 04 (harden-clean-up-optional) — EXECUTING
Phase 4 of 4 (Hardening — optional) — Plan 04-01 closed (audit P1 polish 3/3); 6 plans remain (04-02 build hygiene queued NEXT in Wave 1) Phase 4 of 4 (Hardening — optional) — Plan 04-01 closed (audit P1 polish 3/3); 6 plans remain (04-02 build hygiene queued NEXT in Wave 1)
Plan: 5 of 7 Plan: 6 of 7
Status: Ready to execute Status: Ready to execute
Last activity: 2026-05-21 Last activity: 2026-05-22
Progress: [█████████░] 90% Progress: [█████████░] 90%