Files
mokosh/.planning/STATE.md

86 lines
2.6 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
# Project State
## Project Reference
See: .planning/PROJECT.md (updated 2026-05-15)
**Core value:** When an operator hits a bug, one click MUST produce a
self-contained archive that lets support reproduce what happened — in under 5 s,
no server, no password leaks.
**Current focus:** Phase 1 — Stabilize video pipeline
## Current Position
Phase: 1 of 5 (Stabilize video pipeline)
Plan: 0 of TBD in current phase
Status: Ready to plan
Last activity: 2026-05-15 — bootstrap from intel synthesis (PROJECT.md,
REQUIREMENTS.md, ROADMAP.md, STATE.md written)
Progress: [░░░░░░░░░░] 0%
## Performance Metrics
**Velocity:**
- Total plans completed: 0
- Average duration: —
- Total execution time: —
**By Phase:**
| Phase | Plans | Total | Avg/Plan |
|-------|-------|-------|----------|
| 1. Stabilize video pipeline | 0 | — | — |
| 2. Stabilize DOM + event capture privacy | 0 | — | — |
| 3. Stabilize export pipeline | 0 | — | — |
| 4. SPEC §10 smoke verification | 0 | — | — |
| 5. Harden + clean up | 0 | — | — |
**Recent Trend:**
- Last 5 plans: —
- Trend: —
*Updated after each plan completion*
## Accumulated Context
### Decisions
Decisions are logged in PROJECT.md Key Decisions table (DEC-001 through
DEC-012, all SPEC-Accepted and locked for Phase 1). Recent decisions affecting
current work:
- Phase 1 framing: roadmap treats the existing codebase as a partially-broken
first attempt to be remediated against the SPEC, not as greenfield. The
7 P0 defects from the audit are split across phases 13 along commit
boundaries; phase 4 is end-to-end SPEC §10 smoke verification.
- All 12 SPEC decisions (`DEC-001`..`DEC-012`) are LOCKED for Phase 1.
Changing any of them requires a formal ADR; none are formally LOCKED in the
ingest classification, so a future ADR can revise.
### Pending Todos
None yet.
### Blockers/Concerns
- (informational) `chrome.tabCapture` requires a user gesture on first
activation — Phase 3 (P0-4) restores this by moving the call into the popup
click handler; until Phase 3 lands, recording cannot start cleanly even if
Phase 1's pipeline is correct. Phases 13 should not be re-ordered.
## Deferred Items
Items acknowledged and carried forward from previous milestone close:
| Category | Item | Status | Deferred At |
|----------|------|--------|-------------|
| *(none)* | | | |
## Session Continuity
Last session: 2026-05-15 — bootstrap
Stopped at: Wrote PROJECT.md, REQUIREMENTS.md, ROADMAP.md, STATE.md from
intel synthesis. Coverage validated: 11/11 v1 REQs mapped.
Resume file: None — ready for `/gsd-plan-phase 1`.