5.1 KiB
phase, slug, status, nyquist_compliant, wave_0_complete, created
| phase | slug | status | nyquist_compliant | wave_0_complete | created |
|---|---|---|---|---|---|
| 03 | spec-10-smoke-verification-dom-event-log-verification | draft | false | false | 2026-05-20 |
Phase 03 — Validation Strategy
Per-phase validation contract for feedback sampling during execution.
Phase 3 character: This phase IS validation. The deliverables are harness assertions (A29+) + a §10 sweep VERIFICATION.md, not new production code. The per-task verification map below is filled in by the planner during Plans 03-01..05 creation (each plan task's <automated> block declares its verification command).
Test Infrastructure
| Property | Value |
|---|---|
| Framework | vitest 4.x (unit) + custom Puppeteer harness (UAT — npm run test:uat) |
| Config file | vitest.config.ts + tests/uat/harness.test.ts (orchestrator) |
| Quick run command | npm test -- --run tests/<focused-file>.test.ts |
| Full suite command | npm test -- --run (vitest) + HEADLESS=1 SKIP_PROD_REBUILD=1 npm run test:uat (UAT harness) |
| Estimated runtime | ~50s (vitest 171 tests) + ~95s (UAT harness 29 → ~34 assertions) ≈ 2.5 min full sweep |
Sampling Rate
- After every task commit: Run focused test command (vitest single-file OR
npm run test:uat -- --grep A<NN>for harness) - After every plan wave: Run full vitest + full UAT harness — both MUST be GREEN
- Before
/gsd-verify-work 3: Full suite GREEN + pre-checkpoint bundle gates 6/6 PASS (per saved memoryfeedback-pre-checkpoint-bundle-gates.md) - Max feedback latency: ~2.5 min (full sweep); ~10s (focused vitest); ~20s (focused UAT assertion)
Per-Task Verification Map
| Task ID | Plan | Wave | Requirement | Threat Ref | Secure Behavior | Test Type | Automated Command | File Exists | Status |
|---|---|---|---|---|---|---|---|---|---|
| Filled by planner during Plans 03-01..05 creation | via planner | via planner | via planner | via planner | via planner | via planner | via planner | via planner | ⬜ pending |
Status: ⬜ pending · ✅ green · ❌ red · ⚠️ flaky
Planner instructions: When creating each task in Plans 03-01..05, populate one row in this table with:
Task ID:03-XX-NNformatRequirement: REQ-rrweb-dom-buffer | REQ-user-event-log | REQ-install-clean | (or "N/A — verification surface only")Test Type: harness | unit | bundle-gate | manual-operatorAutomated Command: exact CLI invocation that proves the task succeeded
Wave 0 Requirements
Phase 3 has no Wave 0 (no RED test scaffolds needed — verification phase extends existing harness; new assertions ride established Approach B pattern). All test infrastructure is already in place from Plan 02-04:
- ✅
tests/uat/extension-page-harness.ts— page-side assertA* host - ✅
tests/uat/lib/harness-page-driver.ts— host-side driveA* host - ✅
tests/uat/harness.test.ts— orchestrator - ✅
tests/uat/lib/assertions.ts— shared helpers - ✅
tests/uat/lib/zip.ts— jszip-based archive parsing - ✅
tests/uat/lib/launch.ts— Puppeteer Chrome launch + extension load - ✅
tests/background/no-test-hooks-in-prod-bundle.test.ts— FORBIDDEN_HOOK_STRINGS lockstep - ✅ vitest 4.x + Puppeteer already in package.json
Phase 3 inherits all infrastructure from Phase 1 + 2. wave_0_complete: true (no new infra needed).
Manual-Only Verifications
| Behavior | Requirement | Why Manual | Test Instructions |
|---|---|---|---|
| Extension RAM ≤ 50 MB in background | CON-ram-ceiling (NFR; SPEC §10 #9) | Puppeteer Page.metrics is page-realm only; SW heap requires performance.measureUserAgentSpecificMemory() which throws SecurityError in MV3 (no COOP+COEP). chrome.devtools Memory API requires research budget out of Phase 3 charter. Per D-P3-04: operator/alpha-tester observation. |
Load extension; idle 5 min; open chrome://memory-internals OR chrome://extensions/ → "Service worker" link → DevTools → Memory tab; verify extension background RAM < 50 MB. Plan 03-04 includes the operator-facing instructions verbatim in VERIFICATION.md. Optional puppeteer.Page.metrics scaffolding ships in Plan 03-04 as a best-effort diagnostic with explicit "page-realm only" caveat. |
All other Phase 3 behaviors have automated verification via the UAT harness (Plans 03-01..05 produce assertA29+ for SPEC §10 #4 rrweb DOM, §10 #5 event log, §10 #8 password filter).
Validation Sign-Off
- All tasks have
<automated>verify or Wave 0 dependencies — pending planner fill-in - Sampling continuity: no 3 consecutive tasks without automated verify — verify after planner fills the table
- Wave 0 covers all MISSING references — Phase 3 inherits infra; no Wave 0 needed
- No watch-mode flags — verify in planner output (focused commands use
--run) - Feedback latency < ~2.5 min — confirmed by infrastructure inheritance
nyquist_compliant: trueset in frontmatter — pending sign-off after planner completes
Approval: pending (planner fills per-task map; checker validates)